New Locomotives (8) (ARRA) |
The work to be conducted on the project includes environmental clearance, design, and procurement of eight locomotives complying with the Passenger Rail Investment and Improvement Act (PRIIA) Section 305. The new locomotives will be capable of being equipped with Positive Train Control (PTC) technology once such system is approved by the Federal Rail Administration's (FRA) Office of Safety. The cost includes funding needed for the management of the program. |
PIN#: | 700001C |
DOT Region: | |
Counties: | |
State Route: | 000 |
Location: | Statewide |
Leg Districts: | |
Program / SubProgram: | Public Transportation and Rail |
Sub-Program: | Rail Passenger Capital |
Sub-Category: | |
Improvement Type: | Rail |
Mile Posts: | 0 to 0 |
Project Costs: |
Phase | From - To | Prior | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | 29-31 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Apr-13 - Jun-14 | 5,323,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5,323,000 |
Construction | Jan-14 - Sep-16 | 53,880,000 | 494,000 | 0 | 0 | 0 | 0 | 0 | 0 | 54,374,000 |
Project Totals: | 59,203,000 | 494,000 | 0 | 0 | 0 | 0 | 0 | 0 | 59,697,000 |