Bridge Seismic Retrofit Preservation |
Retrofit bridges statewide to minimize the risk of bridge collapse during seismic events. |
PIN#: | 0BP2004 |
DOT Region: | Headquarters |
Counties: | |
State Route: | 000 |
Location: | |
Leg Districts: | 00 |
Program / SubProgram: | Preservation |
Sub-Program: | Structures Preservation |
Sub-Category: | Catastrophic Reduction |
Improvement Type: | Seismic |
Mile Posts: | 0 to 0 |
Project Costs: |
Phase | From - To | Prior | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | 29-31 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Feb-16 - Apr-20 | 6,597,000 | 1,032,000 | 1,495,000 | 5,500,000 | 5,500,000 | 5,500,000 | 0 | 0 | 25,624,000 |
Right of Way | Jul-13 - Dec-13 | 12,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12,000 |
Construction | Feb-20 - Feb-21 | 21,739,000 | 11,150,000 | 25,448,000 | 38,500,000 | 40,500,000 | 30,500,000 | 0 | 0 | 167,837,000 |
Project Totals: | 28,348,000 | 12,182,000 | 26,943,000 | 44,000,000 | 46,000,000 | 36,000,000 | 0 | 0 | 193,473,000 |