TEIS Home |
|
Nickel/TPA Projects Completed with Minor Ongoing Expenditures |
This line item provides consolidates appropriations transferred from completed TPA and Connecting Washington projects that have Right of Way issues, such as property turnback negotiations, that have or may take several years to resolve. |
PIN#: | 0BI100B |
DOT Region: | Headquarters |
Counties: | |
State Route: | 000 |
Location: | Statewide |
Leg Districts: | 00 |
Program / SubProgram: | Improvement |
Sub-Program: | Mobility |
Sub-Category: | Urban Mobility |
Improvement Type: | |
Mile Posts: | 0 to 0 |
Project Costs: |
Phase | From - To | Prior | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | 29-31 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Right of Way | Jan-00 - Jan-00 | 0 | 616,000 | 0 | 0 | 0 | 0 | 0 | 0 | 616,000 |
Project Totals: | 0 | 616,000 | 0 | 0 | 0 | 0 | 0 | 0 | 616,000 |