SR 516/Wax Rd to 185th Ave SE - Improvements |
This project widens 272nd St SE to four lanes, adding sidewalks, a landscaped median, and planter strips. Illumination and storm drainage collection and water treatment system will be upgraded to current standards. An additional $1.5M was provided in a TIB grant for ROW and construction costs. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Construction | Jul-09 - Jun-10 | 2,096,000 | 382,000 | 322,000 | 0 | 0 | 0 | 0 | 0 | 2,800,000 |
Project Totals: | 2,096,000 | 382,000 | 322,000 | 0 | 0 | 0 | 0 | 0 | 2,800,000 |