I-405/South Renton Vicinity Stage 2 - Widening (Nickel/TPA) |
I-405 is highly congested between the I-5 and the SR 169 interchanges. This project constructs a new half-diamond interchange at SR 515, including an off-ramp from southbound I-405 to SR 515 and an on-ramp from SR 515 to northbound I-405, Adds a north and southbound lane on I-405 between SR 167 and SR 169, and reconstructs the Benson Road Bridge over I-405. These improvements will reduce congestion and improve efficiency. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Jan-08 - May-12 | 12,808,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12,808,000 |
Right of Way | Nov-09 - Oct-12 | 20,276,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20,276,000 |
Construction | Feb-09 - Dec-15 | 131,156,000 | 23,000 | 12,000 | 0 | 0 | 0 | 0 | 0 | 131,191,000 |
Project Totals: | 164,240,000 | 23,000 | 12,000 | 0 | 0 | 0 | 0 | 0 | 164,275,000 |