TEIS Home |
|
I-405/I-90 to SE 8th St - Widening |
I-405 is highly congested at this location. This project will construct one additional lane in the northbound and southbound directions between I-90 and SE 8th St. This will reduce congestion on I-405. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Aug-03 - Jun-15 | 28,587,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 28,587,000 |
Right of Way | Jan-06 - Jun-07 | 46,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 46,000 |
Construction | Feb-07 - Dec-17 | 146,183,000 | 0 | 5,000,000 | 0 | 0 | 0 | 0 | 0 | 151,183,000 |
Project Totals: | 174,816,000 | 0 | 5,000,000 | 0 | 0 | 0 | 0 | 0 | 179,816,000 |