TEIS Home |
|
I-405/SR 181 to SR 167 - Widening |
I-405 is highly congested in Tukwila in the vicinity of I-5. One additional general purpose lane will be constructed northbound on I-405 from SR 181 to SR 167. The southbound HOV lane on SR 167 will be extended north to I-405. This will reduce congestion. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Nov-05 - Jul-07 | 25,515,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 25,515,000 |
Right of Way | Jan-06 - Jun-11 | 6,482,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 6,482,000 |
Construction | Jun-07 - Jun-21 | 107,848,000 | 101,000 | 98,000 | 0 | 0 | 0 | 0 | 0 | 108,047,000 |
Project Totals: | 139,845,000 | 101,000 | 98,000 | 0 | 0 | 0 | 0 | 0 | 140,044,000 |