SR 290/Spokane River E Trent Br - Replace Bridge |
The bridge is structurally deficient. Replacing the existing bridge with a new bridge designed to current standards will eliminate the possibility of catastrophic failure. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Jan-16 - Feb-20 | 783,000 | 1,385,000 | 267,000 | 0 | 0 | 0 | 0 | 0 | 2,435,000 |
Right of Way | Jul-17 - Feb-20 | 0 | 50,000 | 301,000 | 0 | 0 | 0 | 0 | 0 | 351,000 |
Construction | Dec-19 - Oct-23 | 0 | 0 | 13,837,000 | 6,900,000 | 0 | 0 | 0 | 0 | 20,737,000 |
Project Totals: | 783,000 | 1,435,000 | 14,405,000 | 6,900,000 | 0 | 0 | 0 | 0 | 23,523,000 |