I-90/Snoqualmie Pass East - Hyak to Keechelus Dam - Corridor Improvement |
The section of I-90 between Hyak and Lake Keechelus Dam experiences congestion due to increasing traffic volumes and closures for avalanche control. By adding lanes to this section and realigning the roadway, the project will decrease congestion, minimize closures due to avalanche control, and increase safety. This funding includes repayment of underpaid sales tax per agreement with the Department of Revenue. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Dec-13 - Jun-17 | 74,485,000 | 281,000 | 0 | 0 | 0 | 0 | 0 | 0 | 74,766,000 |
Right of Way | Dec-12 - Jun-17 | 6,465,000 | 21,000 | 165,000 | 0 | 0 | 0 | 0 | 0 | 6,651,000 |
Construction | Dec-19 - May-32 | 392,621,000 | 69,574,000 | 17,474,000 | 1,743,000 | 523,000 | 523,000 | 523,000 | 523,000 | 483,504,000 |
Project Totals: | 473,571,000 | 69,876,000 | 17,639,000 | 1,743,000 | 523,000 | 523,000 | 523,000 | 523,000 | 564,921,000 |