I-82/Valley Mall Blvd - Rebuild Interchange |
The Valley Mall Boulevard Interchange suffers congestion and has experienced a number of collisions. This project will rearrange the interchange to increase safety, relieve congestion and improve traffic flow movements. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Jun-04 - Apr-10 | 3,525,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3,525,000 |
Right of Way | Nov-06 - Jun-18 | 5,717,000 | 1,000 | 21,000 | 0 | 0 | 0 | 0 | 0 | 5,739,000 |
Construction | Feb-10 - Apr-14 | 25,539,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 25,539,000 |
Project Totals: | 34,781,000 | 1,000 | 21,000 | 0 | 0 | 0 | 0 | 0 | 34,803,000 |