TEIS Home |
|
SR 6/Rock Creek Br E - Replace Bridge |
Current bridge is beyond its service life and too narrow in width. Replacing existing bridge with a new bridge that meets current standards. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Jun-06 - Sep-13 | 1,416,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1,416,000 |
Right of Way | Jan-13 - Dec-17 | 307,000 | 116,000 | 0 | 0 | 0 | 0 | 0 | 0 | 423,000 |
Construction | Jan-14 - Jun-17 | 8,351,000 | 5,000 | 50,000 | 0 | 0 | 0 | 0 | 0 | 8,406,000 |
Project Totals: | 10,074,000 | 121,000 | 50,000 | 0 | 0 | 0 | 0 | 0 | 10,245,000 |