SR 109/Moclips River Bridge - Replace Bridge |
The existing bridge design which includes 54 wooden piling, traps debris and requires repetitive channel clearing of logs and other types of debris. This project will replace the existing structure eliminating the need for continual maintenance and the associated environmental impacts. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | May-06 - Mar-35 | 730,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 730,000 |
Right of Way | Sep-16 - Dec-34 | 28,000 | 0 | 0 | 0 | 0 | 0 | 0 | 407,000 | 435,000 |
Construction | Feb-35 - Jun-35 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 4,906,000 | 4,906,000 |
Project Totals: | 758,000 | 0 | 0 | 0 | 0 | 0 | 0 | 5,313,000 | 6,071,000 |