US 101/Gardiner Vicinity - Add Climbing Lane |
This section of US 101 experiences backups due to high truck volumes and steep grades. This project constructs a northbound truck climbing lane to reduce congestion and improve motorist safety. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Mar-93 - Jun-26 | 384,000 | 0 | 0 | 0 | 0 | 0 | 0 | 68,000 | 452,000 |
Right of Way | Jul-25 - Jun-26 | 1,000 | 0 | 0 | 0 | 0 | 0 | 0 | 80,000 | 81,000 |
Construction | Aug-26 - Jun-27 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2,027,000 | 2,027,000 |
Project Totals: | 385,000 | 0 | 0 | 0 | 0 | 0 | 0 | 2,175,000 | 2,560,000 |