I-5/Tacoma HOV Improvements (Nickel/TPA) |
This segment of I-5 experiences congestion and mobility problems due to high traffic volumes and is identified as part of the core HOV program. This project constructs HOV lanes from South 48th Street to the King County line. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Feb-12 - Jan-18 | 164,541,000 | 4,203,000 | 391,000 | 0 | 0 | 0 | 0 | 0 | 169,135,000 |
Right of Way | May-10 - Jun-15 | 27,974,000 | 1,083,000 | 0 | 0 | 0 | 0 | 0 | 0 | 29,057,000 |
Construction | Aug-17 - Sep-24 | 728,568,000 | 213,430,000 | 153,824,000 | 89,319,000 | 17,373,000 | 0 | 0 | 77,840,000 | 1,280,354,000 |
Project Totals: | 921,083,000 | 218,716,000 | 154,215,000 | 89,319,000 | 17,373,000 | 0 | 0 | 77,840,000 | 1,478,546,000 |