SR 285/W End of George Sellar Bridge - Intersection Improvements |
The current intersection is a major bottleneck to traffic. The intersection of SR 285 and Mission St. will be modified. This will increase the flow through the intersection, reducing travel time and congestion related collisions on SR 285 and the local roadway network. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Nov-05 - Jun-12 | 3,348,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3,348,000 |
Right of Way | Sep-08 - Dec-13 | 2,552,000 | 6,000 | 3,000 | 0 | 0 | 0 | 0 | 0 | 2,561,000 |
Construction | May-12 - May-14 | 11,528,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 11,528,000 |
Project Totals: | 17,428,000 | 6,000 | 3,000 | 0 | 0 | 0 | 0 | 0 | 17,437,000 |