SR 99/Aurora Bridge - Painting |
Clean and paint bridge in order to preserve its structural integrity. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | May-16 - Dec-17 | 961,000 | 379,000 | 0 | 0 | 0 | 0 | 0 | 0 | 1,340,000 |
Right of Way | Nov-14 - Jun-15 | 80,000 | 136,000 | 0 | 0 | 0 | 0 | 0 | 0 | 216,000 |
Construction | Nov-17 - Apr-20 | 16,933,000 | 21,891,000 | 10,934,000 | 0 | 0 | 0 | 0 | 0 | 49,758,000 |
Project Totals: | 17,974,000 | 22,406,000 | 10,934,000 | 0 | 0 | 0 | 0 | 0 | 51,314,000 |