SR 9/Pilchuck Creek - Replace Bridge |
This project will replace the existing bridge which is very narrow (about 17 feet wide) with a new one that will meet current design standards. The project will include improving the deficient roadway from both ends. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Sep-14 - Sep-15 | 2,755,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2,755,000 |
Right of Way | Jun-11 - Feb-15 | 1,160,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1,160,000 |
Construction | Apr-15 - Mar-17 | 11,459,000 | 15,000 | 145,000 | 0 | 0 | 0 | 0 | 0 | 11,619,000 |
Project Totals: | 15,374,000 | 15,000 | 145,000 | 0 | 0 | 0 | 0 | 0 | 15,534,000 |