TEIS Home |
|
SR 9/176th Street SE to SR 96 - Widening |
This project will widen SR 9 from 176th St. SE vicinity to SR 96 vicinity to provide an additional northbound lane and improve the performance of several intersections by providing right and left turn lanes, signal and lighting upgrades, provision for U-turn movements, and ADA upgrades. Other work includes stormwater treatment facilities, roadside improvements, and signing upgrades. |
Project Costs: |
Phase | From - To | Prior | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | 27-29 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Jul-13 - Jun-20 | 2,702,000 | 1,115,000 | 2,080,000 | 0 | 0 | 0 | 0 | 0 | 5,897,000 |
Right of Way | Aug-18 - Dec-19 | 0 | 0 | 6,344,000 | 0 | 0 | 0 | 0 | 0 | 6,344,000 |
Construction | Jan-00 - Jan-00 | 0 | 1,000,000 | 8,738,000 | 0 | 0 | 0 | 0 | 0 | 9,738,000 |
Project Totals: | 2,702,000 | 2,115,000 | 17,162,000 | 0 | 0 | 0 | 0 | 0 | 21,979,000 |