TEIS Home TEIS
Home
HSR Program Closeout
Project close out activities such as final documentation controls and archiving, final reporting, commitments database updates, and administrative management. The final ARRA reimbursements must be submitted July 2017, these funds would provide for up to 5 WSDOT personnel or consultants, to close the program.
 PIN#:  HSR006
 DOT Region:  Headquarters
 Counties:  
 State Route:  000
 Location:  
 Leg Districts:  
 Program / SubProgram:  Public Transportation and Rail
 Sub-Program:  Rail Passenger Capital
 Sub-Category:  
 Improvement Type:  
 Mile Posts: 0 to 0    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Construction Jul-17 - Jul-17 00500,00000000500,000
  Project Totals:  0 0 500,000 0 0 00 0 500,000