TEIS Home TEIS
Home
MV Chetzemoka Improvement
Targeted improvements for the MV Chetzemoka are investments that address existing deficiencies, enhance efficiency, and meet other needs to maintain and support existing service levels. An existing deficiency is a situation where there is a clear equipment limitation that would pose a serious safety or operational challenge if left unmitigated. A targeted improvement may be made to replace vital components that have become obsolete, not supported by the manufacturer, or to take advantage of new technology available.
 PIN#:  944476B
 DOT Region:  WA St Ferries
 Counties:  Island,Jefferson,King,Pierce
 State Route:  000
 Location:  Chetzemoka
 Leg Districts:  10, 24
 Program / SubProgram:  Marine Capital - W4
 Sub-Program:  
 Sub-Category:  
 Improvement Type:  Marine Vessel
 Mile Posts: 0 to 0    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Jul-17 - Jun-31 357,00013,0002,0006,0007,00033,00033,00079,000530,000
Construction Aug-18 - Jun-31 1,110,0007,00082,00054,00062,000296,000296,000710,0002,617,000
  Project Totals:  1,467,000 20,000 84,000 60,000 69,000 329,000329,000 789,000 3,147,000