New Locomotives (8) (ARRA)
The work to be conducted on the project includes environmental clearance, design, and procurement of eight locomotives complying with the Passenger Rail Investment and Improvement Act (PRIIA) Section 305. The new locomotives will be capable of being equipped with Positive Train Control (PTC) technology once such system is approved by the Federal Rail Administration's (FRA) Office of Safety. The cost includes funding needed for the management of the program.
 PIN#:  700001C
 DOT Region:  
 Counties:  
 State Route:  000
 Location:  Statewide
 Leg Districts:  
 Program / SubProgram:  Public Transportation and Rail
 Sub-Program:  Rail Passenger Capital
 Sub-Category:  
 Improvement Type:  Rail
 Mile Posts: 0 to 0    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Apr-13 - Jun-14 4,215,0001,108,00017,000000005,340,000
Construction Jan-14 - Sep-16 2,715,00032,591,00019,228,0000000054,534,000
  Project Totals:  6,930,000 33,699,000 19,245,000 0 0 00 0 59,874,000