Corridor Reliability Supplemental Work (ARRA)
Prepares a project-level NEPA documentation, PE and FD,and constructs improvements._This project will increase service reliability on the PNWRC by constructing improvements to prevent weather-related incidents and to mitigate the impacts that disrupt the service along the BNSF main line between Blaine, WA and Vancouver, WA. This is a redistribution from Ohio.
 PIN#:  700000F   Project Page
 DOT Region:  
 Counties:  
 State Route:  000
 Location:  Westside
 Leg Districts:  
 Program / SubProgram:  Public Transportation and Rail
 Sub-Program:  Rail Passenger Capital
 Sub-Category:  
 Improvement Type:  Railroad Improvements
 Mile Posts: 0 to 0    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Dec-12 - Jul-14 1,900,000-89,0002,000000001,813,000
Construction Aug-13 - Aug-15 2,786,00013,157,000485,0000000016,428,000
  Project Totals:  4,686,000 13,068,000 487,000 0 0 00 0 18,241,000