I-405/NE 44th St to 112th Ave SE - Widening
This is the state's $150M match to potential Regional funding, which is required to complete the overall project. Ultimately the SR 169 to I-90 project will include construction of two additional general purpose lanes in each direction and transit improvements including park and ride expansion and HOV direct access ramps. This section of I-405 is a major choke point on I-405 due to the existing roadway being one lane narrower than I-405 north of I-90.
 PIN#:  840508A   Project Page
 DOT Region:  Northwest
 Counties:  King
 State Route:  405
 Location:  Renton to Bellevue   Locate Project
 Leg Districts:  41
 Program / SubProgram:  Improvement
 Sub-Program:  Mobility
 Sub-Category:  Urban Mobility
 Improvement Type:  Rural/Urban Mobility - General Purpose
 Mile Posts: 7 to 9.5    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Jan-06 - Jul-26 3,274,90200000003,274,902
Right of Way Jan-06 - Jun-27 1,469,98700000001,469,987
Construction Jan-00 - Jan-00 750,0000000000750,000
  Project Totals:  5,494,889 0 0 0 0 00 0 5,494,889