Concrete Rehabilitation Program (Nickel)
In several locations statewide the existing concrete pavement is approaching or exceeding 40 years of age and is in need of repair or replacement. This project replaces or provides interim repairs to concrete pavement at six locations as well as providing preliminary design and environmental analysis for future projects of this kind on I-5 between the Boeing Access Road and Northgate.
 PIN#:  800515C   Project Page
 DOT Region:  Northwest
 Counties:  King
 State Route:  005
 Location:  I-5   Locate Project
 Leg Districts:  11, 32, 37, 43, 46
 Program / SubProgram:  Preservation
 Sub-Program:  Roadway Preservation
 Sub-Category:  Paving
 Improvement Type:  PCCP (Concrete Replacement)
 Mile Posts: 0 to 0    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Jul-19 - Nov-21 1,026,0003,318,0001,244,0003,950,0001,218,00000010,756,000
Construction Nov-20 - Jun-23 29,549,0009,487,00055,983,00020,058,00048,971,00017,923,00000181,971,000
  Project Totals:  30,575,000 12,805,000 57,227,000 24,008,000 50,189,000 17,923,0000 0 192,727,000