US 395/NSC-Francis Ave to Farwell Rd - New Alignment
Spokane lacks adequate capacity for North/South traffic through Spokane from I-90 north. Constructing two lanes between Farwell Road and Francis Avenue and completing the grading between US 2 and Wandermere will increase capacity and reduce travel time and delays on this section of the new North Spokane Corridor (NSC). Individual sections of the corridor will be designed and constructed under separate projects. Tiger Grant funding was provided to construct the southbound lane of the project.
 PIN#:  600001A   Project Page
 DOT Region:  Eastern
 Counties:  Spokane
 State Route:  395
 Location:  Spokane   Locate Project
 Leg Districts:  03, 04, 06, 07
 Program / SubProgram:  Improvement
 Sub-Program:  Mobility
 Sub-Category:  Urban Mobility
 Improvement Type:  Rural/Urban Mobility - General Purpose
 Mile Posts: 161.45 to 167.86    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Jul-03 - Jun-09 8,284,00000000008,284,000
Right of Way Sep-03 - Oct-15 54,581,000000000054,581,000
Construction Mar-04 - Aug-16 146,552,0003,000000000146,555,000
  Project Totals:  209,417,000 3,000 0 0 0 00 0 209,420,000