I-90/Snoqualmie Pass East - Hyak to Keechelus Dam - Corridor Improvement
The section of I-90 between Hyak and Lake Keechelus Dam experiences congestion due to increasing traffic volumes and closures for avalanche control. By adding lanes to this section and realigning the roadway, the project will decrease congestion, minimize closures due to avalanche control, and increase safety. This funding includes repayment of underpaid sales tax per agreement with the Department of Revenue.
 PIN#:  509009B   Project Page
 DOT Region:  South Central
 Counties:  Kittitas
 State Route:  090
 Location:  Hyak-Easton Vicinity   Locate Project
 Leg Districts:  05, 13
 Program / SubProgram:  Improvement
 Sub-Program:  Economic Initiatives
 Sub-Category:  Freight and Goods
 Improvement Type:  Rural/Urban Mobility - General Purpose
 Mile Posts: 55.1 to 64.3    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Dec-13 - Jun-17 73,830,000631,00054,0000000074,515,000
Right of Way Dec-12 - Jun-17 6,388,000187,00072,000000006,647,000
Construction Dec-19 - May-32 270,937,000132,416,00072,548,0003,543,0002,182,000528,000528,0001,056,000483,738,000
  Project Totals:  351,155,000 133,234,000 72,674,000 3,543,000 2,182,000 528,000528,000 1,056,000 564,900,000