SR 500/St Johns Blvd - Build Interchange
The intersection at SR 500 and St. Johns Boulevard has been identified as a high collision location. Removing the intersection at SR 500 and St. Johns Boulevard and constructing a new bridge over SR 500 will reduce the frequency of collisions.
 PIN#:  450000A   Project Page
 DOT Region:  Southwest
 Counties:  Clark
 State Route:  500
 Location:  Vancouver   Locate Project
 Leg Districts:  49
 Program / SubProgram:  Improvement
 Sub-Program:  Safety
 Sub-Category:  Collision Prevention
 Improvement Type:  At Grade Intersections (Urban) - (NHS Multi-lane>45 mph)
 Mile Posts: 0.42 to 1.55    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Nov-05 - Mar-11 7,414,00000000007,414,000
Right of Way Mar-07 - Jun-15 4,838,00000000004,838,000
Construction Mar-11 - Oct-16 32,680,00089,00000000032,769,000
  Project Totals:  44,932,000 89,000 0 0 0 00 0 45,021,000