I-205/Mill Plain Interchange to NE 18th St - Build Interchange - Stage 2
The section of I-205 from Mill Plain Road to NE 18th needs relief from congestion. By constructing a new northbound off ramp and southbound on ramp at NE 18th Street the project will reduce congestion to improve traffic flow.
 PIN#:  420511A   Project Page
 DOT Region:  Southwest
 Counties:  Clark
 State Route:  205
 Location:  Vancouver   Locate Project
 Leg Districts:  49
 Program / SubProgram:  Improvement
 Sub-Program:  Mobility
 Sub-Category:  Urban Mobility
 Improvement Type:  Urban Mobility - Interchange New or Rebuild
 Mile Posts: 27.22 to 30.28    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Aug-06 - Nov-14 5,746,00000000005,746,000
Right of Way Sep-08 - Jun-17 1,612,000447,0000000002,059,000
Construction Aug-14 - Dec-17 10,864,00020,443,0001,542,0000000032,849,000
  Project Totals:  18,222,000 20,890,000 1,542,000 0 0 00 0 40,654,000