TEIS Home |
|
US 101/Hoh River (Site #2) - Stabilize Slopes |
This section of US 101 is at risk for erosion from the Hoh River. Work will consist of installing six engineered log jams in the Hoh River adjacent to US 101 for bank stabilization and two engineered log jams upstream for channel diversion preventing the loss of the roadway due to the Hoh River bank erosion. |
Project Costs: |
Phase | From - To | Prior | 15-17 | 17-19 | 19-21 | 21-23 | 23-25 | 25-27 | Future | Total |
---|---|---|---|---|---|---|---|---|---|---|
Preliminary Engineering | Jul-05 - Jul-14 | 2,019,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2,019,000 |
Right of Way | Aug-09 - Jun-15 | 70,000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 70,000 |
Construction | May-14 - Jun-16 | 2,675,000 | 48,000 | 0 | 0 | 0 | 0 | 0 | 0 | 2,723,000 |
Project Totals: | 4,764,000 | 48,000 | 0 | 0 | 0 | 0 | 0 | 0 | 4,812,000 |