SR 285/W End of George Sellar Bridge - Intersection Improvements
The current intersection is a major bottleneck to traffic. The intersection of SR 285 and Mission St. will be modified. This will increase the flow through the intersection, reducing travel time and congestion related collisions on SR 285 and the local roadway network.
 PIN#:  228501X   Project Page
 DOT Region:  North Central
 Counties:  Chelan
 State Route:  285
 Location:  South Wenatchee   Locate Project
 Leg Districts:  12
 Program / SubProgram:  Improvement
 Sub-Program:  Mobility
 Sub-Category:  Urban Mobility
 Improvement Type:  Urban Mobility - Interchange New or Rebuild
 Mile Posts: 0.28 to 1.14    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Nov-05 - Jun-12 3,348,00000000003,348,000
Right of Way Sep-08 - Dec-13 2,540,00020,0000000002,560,000
Construction May-12 - May-14 11,465,00069,00000000011,534,000
  Project Totals:  17,353,000 89,000 0 0 0 00 0 17,442,000