SR 28/Jct US 2 and US 97 to 9th St, Stage 1 - New Alignment
SR 28 is heavily congested mainly due to local traffic connecting to the intersection of US 2/97 and SR 28. This stage will extend Eastmont Ave to the intersection of US 2/97 and SR 28 and constructs needed improvements at the intersection. This will reduce congestion on SR 28 and the congestion related collisions.
 PIN#:  202800D   Project Page
 DOT Region:  North Central
 Counties:  Douglas
 State Route:  028
 Location:  East Wenatchee   Locate Project
 Leg Districts:  12
 Program / SubProgram:  Improvement
 Sub-Program:  Mobility
 Sub-Category:  Rural Mobility
 Improvement Type:  Rural/Urban Mobility - General Purpose
 Mile Posts: 0.01 to 0.25    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering May-06 - Nov-11 6,602,0001,0000000006,603,000
Right of Way Mar-07 - Dec-13 6,051,000406,000437,000000006,894,000
Construction Oct-09 - Dec-13 26,218,000379,00000000026,597,000
  Project Totals:  38,871,000 786,000 437,000 0 0 00 0 40,094,000