SR 9/212th St SE to 176th St SE, Stage 3 - Add Lanes
This section of SR 9 experiences severe congestion and operational problems due to large traffic volumes due rapid commercial and residential development. This section also falls within a High Accident Corridor (HAC) as identified in the 2000 Safety Management System. To address capacity needs, enhance traffic operations and reduce the number and severity of accidents, SR 9 will be widened from two lanes to four lanes, plus a raised median. Sidewalks will be constructed in selected locations on both sides of SR 9. Other minor work will be performed as needed. This is Stage 3 of the overall work on this corridor.
 PIN#:  100900F   Project Page
 DOT Region:  Northwest
 Counties:  Snohomish
 State Route:  009
 Location:  Clearview Southerly   Locate Project
 Leg Districts:  01
 Program / SubProgram:  Improvement
 Sub-Program:  Mobility
 Sub-Category:  Urban Mobility
 Improvement Type:  Rural/Urban Mobility - General Purpose
 Mile Posts: 1.83 to 4.22    
  Project Costs:
Phase From - To Prior 15-17 17-19 19-21 21-23 23-2525-27 Future Total
Preliminary Engineering Jan-04 - Nov-11 8,234,00000000008,234,000
Right of Way Dec-07 - Oct-16 14,635,00040,00000000014,675,000
Construction Jun-11 - Jun-16 29,770,000862,00000000030,632,000
  Project Totals:  52,639,000 902,000 0 0 0 00 0 53,541,000